Tasks and schedule     << backoverviewnext >>

The task list visualizes the current status of each task on a timeline. Details of the schedule are displayed in a pop-up when the mouse is moved over a timeline.

Aufgabenstatus

The graph shows a timeline for a period of 60 days, 30 before and 30 after the current date. The size of the current node is determined by the amount of working days assigned to it.

This way, users can assess the urgency of a task at a glance.

<< backoverviewnext >>

Aufgabenstatus
The task is delayed by four days

Aufgabenstatus
The task was assigned ten days, and is due in four